The Ghana Grid Company Limited (GRIDCo) says damage to its 330kV transmission line from Aboadze to Anwomaso has disrupted electricity supply to parts of the Western and Ashanti regions after chainsaw operators felled a large tree onto the transmission infrastructure.
The incident occurred late Wednesday afternoon, November 25, 2026, causing the transmission line to trip and interrupting power supply.
In a statement issued from Tema, GRIDCo said investigations by its engineers, following a patrol of the affected section, established that a large tree had been brought down onto the line.
The company attributed the damage to chainsaw operations in the area.
Kumasi power supply affected
The outage has affected electricity supply in parts of the Western and Ashanti regions, with GRIDCo indicating that the loss of the transmission line had forced system operators to reduce power supplied to parts of Kumasi.
The 330kV Aboadze to Anwomaso line is a critical part of the country's transmission network, and its unavailability has placed pressure on the electricity supply arrangements serving the affected areas.
GRIDCo did not specify the number of consumers affected or provide a definite timeline for completing the repairs.
GRIDCo engineers working to restore supply
The company said its technical teams were working to repair the damaged infrastructure and return the transmission line to service.
“Every effort is being made to remedy the situation,” GRIDCo said, adding that engineers were undertaking the necessary repairs to restore the line as quickly as possible.
The company apologised to consumers experiencing interruptions and assured the public that power would be restored once the repair works were completed.
The incident has raised concerns about the risks of uncontrolled tree felling around critical electricity transmission infrastructure, particularly where such activities can damage high-voltage lines and affect power supply across multiple regions.