Kpong-Tema pipeline maintenance will interrupt water supply across Tema, eastern Accra and parts of the Eastern Region from Thursday, August 6, to Saturday, August 8, Ghana Water Ltd has announced.
The three day exercise will require the temporary shutdown of the Kpong Water Treatment Plant while engineers isolate and replace weak sections of the 21 inch and 42 inch transmission pipelines.
Customers connected to the Kpong Water Supply System should expect either no water or reduced pressure during the work.
More than 300 metres marked for replacement
Routine engineering inspections found more than 300 metres of deteriorated pipeline requiring urgent attention. Five sections of different lengths will be isolated and replaced during the shutdown, according to the company’s maintenance notice.
Ghana Water said acting now should reduce the risk of major bursts, emergency shutdowns and avoidable losses along the transmission network.
The Kpong plant is Ghana’s largest treatment facility by design capacity and supplies Tema, Accra East and some rural communities in the Eastern Region.
The work is planned maintenance, but its scale is substantial. Two major pipelines must be handled within a narrow window without extending the interruption beyond Saturday.
That matters because a failure on either main line can quickly affect water delivery across several densely populated districts at once.
Communities facing the interruption
The affected zone covers Gbetsele, Ashaiman, Katamanso, Zenu, Atadeka, Afienya, Appolonia, Prampram, Kpone and Dawhenya. Every community within the Tema Metropolis is also included.
Residents in Spintex, Baatsona, Sakumono, Nungua and Teshie should prepare for the same disruption. Farther north, the notice names Kpong, Akuse, Somanya, Atimpoku and nearby towns.
For households, the practical message is simple: water available before Thursday may have to last through the maintenance period.
Ghana Water has asked affected customers to “store adequate quantities of water” before the shutdown and use those supplies carefully.
Hospitals, health facilities and other essential service providers have been advised to make contingency arrangements rather than rely on normal pipeline supply.
Water tankers will be sent to selected critical institutions where that is feasible. The company did not announce a general tanker distribution programme for residential communities.
Engineers working against the clock
Technical teams are expected to work continuously throughout the three days. Ghana Water said normal supply would be restored as quickly as possible once the replacements and necessary checks are completed.
Updates will be issued through the company’s official communication channels, including confirmation when full supply has returned.
The repair is meant to strengthen a transmission system serving a heavily populated stretch of Greater Accra and the Eastern Region. Three days is the target. For homes with limited storage, it will still feel like a long interruption.
READ ALSO: MTN Ghana's Interim Dividend Totals Six Pesewas as State Payments Near GH¢6bn